This £4 million project was completed over the course of 27 weeks and works included a full Cat A refurbishment to levels 2 – 6 including WC’s and common parts. A phased refurbishment of the live reception took place including the formation of new stairs to take the installation of a Sesame lift. The renewal of curtain walling, feature metal mesh walls and reception desk completed the refurbishment.

A complex structural riser was formed, running from basement to level 7 plant room for future use by basement tenants.

  • Project

    130 Jermyn Street

  • Value

    £4 million

  • Duration

    27 weeks

  • Project Manager

    Cube

  • Architect

    Gensler

  • QS

    Alinea

  • Services Consultant

    MTT

Project Director

Alex English

Related Projects

Alex English

Project Director

Alex has recently joined Collins as Project Director, where he is responsible for delivering projects on time and to a high standard, while prioritising health and safety.

He started his career as a carpenter, navigating various operational roles. As a Project Director, he leverages his expertise to address challenges and find innovative solutions that benefit all stakeholders involved in projects.

This website uses cookies to ensure the best possible experience for the user. Please accept or decline. See our cookie policy for more information