Carried out on behalf of a global investment and advisory firm, this 7,000sq ft Cat A refurbishment took place over the course of 12 weeks. Works included a soft strip of the existing space followed by the installation of new raised access flooring throughout, exposed M&E services, window restrictors, doors and door compartments and a new fire alarm system throughout.

Working within an occupied building meant noisy working hours had to be strictly adhered to in order to minimise any disturbance to surrounding tenants The £800,000 project in High Holborn House was handed over to schedule October 2015.

  • Project

    High Holborn House

  • Value

    £800,000

  • Duration

    12 weeks

  • Project Manager

    Beadmans

  • Architect

    BGY

  • QS

    Beadmans

  • Structural Engineers

    MIT