Collins were awarded the contract to upgrade the London Planetarium building, part of Madam Tussauds complex, in order to house the new Marvel Super Heroes 4D cinema.

The works included preparation of the famous domed auditorium in order to take the supports and screen, new structure floor levels and special effects seating and lighting.

Collins worked in conjunction with Merlin and Kraftwerk - world leaders in CGI feature films and 4D attractions, and in close collaboration Madame Tussauds creative team.

  • Project

    Marylebone Road London NW1

  • Value

    £364,000

  • Duration

    12 Weeks

  • Project Manager

    MCL Projects

  • QS

    Cullum Morris Powells

  • Services Consultant

    Engineering Design Partnership

Related Projects