A 150,000 sq ft strip out and CAT A fit out across levels 1, 2, 5 & 6 of this office building situated in the heart of St Katherine’s Dock. The warehouse style space boasts new exposed services, raised access floor, lift lobbies and WC’s. External decking was also installed to allow incoming tenants to make the most of the spectacular views.
The existing reception was upgraded with new flooring, reception desk, wall panelling and light fittings to reflect the rest of the work and a new bike store and showers were installed on the lower ground floor. The work was completed on time after 27 weeks on site.
-
Project
1 St Katherine's Way
-
Value
£12 million
-
Duration
27 weeks
-
Project Manager
Beadmans
-
Architect
JRA
-
QS
Beadmans
-
Services Consultant
MTT
Divisional Director
Duncan Redman
Related Projects
Duncan Redman
Divisional Director
Duncan joined Collins in 2001 and has been a part of, and contributed to, the growth, development and success of the company. Having worked in the industry for over 30 years, Duncan has a wealth of experience and knowledge across a range of project types, from Cat B fit out to cut and carve refurbishment.
Duncan leads a committed, hardworking team who go the extra mile at every level to deliver a successful project. He believes in a hands on approach and management style, and leads his teams by example. He builds strong, honest relationships with clients which as a result, has consistently led to repeat business.